škoda 2024

Tunnel progress as HS2’s ‘Florence’ and ‘Cecilia’ reach Little Missenden


posted on 8th Aug 2023 11:56


On 8 August 2023 HS2 confirmed that ‘Florence’ and ‘Cecilia’ - the two giant tunnelling machines digging HS2’s longest tunnels - have reached the Little Missenden ventilation shaft, more than three quarters of the way through their 10 mile drive under the Chilterns.

The enormous 2,000 tonne machines have spent two years excavating the twin tunnels between the M25 and South Heath in Buckinghamshire that will help improve connections between London, Birmingham and the North. Each machine is a 170 m long self-contained underground factory, digging the tunnel, lining it with 56,000 concrete segments to form rings and grouting them into place as it moves forward. Designed specifically for the geology of the Chilterns, the first TBMs were launched in Summer 2021 from a site near the M25 and have already excavated approximately 2 million cubic metres of chalk and flint. 

As well as digging and lining the tunnels, engineers have also completed the excavation of five shafts that will provide ventilation and emergency access near Chalfont St Peter, Chalfont St Giles, Amersham and Little Missenden with an intervention shaft at Chesham Road. The 35 m deep shaft near Little Missenden - which the TBMs have now reached - is next to the A413 about half a mile from the Buckinghamshire village. A ‘headhouse’ will be built on top of the shaft to house ventilation and safety equipment, designed to resemble local farm buildings with new planting to help blend it into the surrounding landscape.

The news comes just weeks after planning consent was granted by Buckinghamshire Council for the North Portal of the tunnel under Schedule 17 of the HS2 Act, meaning that all major design elements now have consent. The two TBMs are operated by, Align - a joint venture formed of Bouygues Travaux Publics, Sir Robert McAlpine, and VolkerFitzpatrick. Each machine has a crew of around 15 people, working in shifts and supported by over 100 people on the surface, managing the logistics and maintaining the smooth progress of the tunnelling operation.

Approximately 2.7 million cubic metres of material - mostly chalk and flint - will be excavated during the construction of the tunnels and used for landscaping. Once construction is complete, the temporary buildings at the south portal will be removed and the site landscaped with around 90 hectares of wildlife-rich chalk grassland habitats. Chalk grassland used to be widespread across the hills of southeast England and are considered habitat of international conservation significance with just 700 ha left across the Chilterns.

HS2 currently has five TBMs in the ground, with a further five due to be launched over the coming years. Together they will create 64 miles of tunnel between London and the West Midlands including major tunnels on the approach to London and Birmingham.

Related news
Tags
HS2
Share